Tonbridge Vets

Refurbishment of existing building into new veterinary surgery.

Completed July 2021

Meopham Veterinary Hospital

Theobald’s were awarded these works by a long term client and involved the full refurbishment of an existing office building into a new vets.

The works involved the strip out of various rooms, new partitions to form  store rooms and theatre room, new flooring throughout all areas, decoration to all areas, new x-ray rated doors to theatre room, including specialist boarding to walls, full electrical works including new power and lighting, new sink units to most rooms, refurbishment of reception desk and new aluminum windows and doorsets to front and side elevations. Air conditioning was also installed to various parts of the surgery, along with extract fans to various areas. The works also included a new tarmac drive to the front of the building including drainage and levelling out of the back garden for the installation of a timber shed by others.

The project was completed during the covid pandemic so material sourcing was an issue, but all materials were procured successfully to enable the completion of works. We also limited numbers on site throughout the contract period to comply with the social distancing regulations.

Newtons Court, Dartford

New mezzanine installation and associated refurbishment works, Newtons Court.

Completed July 2022

Dartford and Gravesham NHS Trust

Theobald’s were awarded these works by a new NHS trust client and the works consisted of forming a new mezzanine floor within the main part of the commercial unit to form new workshop space as well as additional storage space on the top of the new mezzanine.

The works included a full M&E installation to new and existing areas, including new lighting, power, ventilation and air conditioning. Formation of  new heavy duty partitions around the perimeter of mezzanine, new glass partitions to ground and first floor office areas, kitchenette within main workshop area, suspended ceiling, flooring, decorating and new doorsets.

This project had some issues with lead times with the mezzanine floor and other materials, but was completed on programme and within budget.