Dartford Civic Centre
Dartford Borough Council
2018 – September 2020
This project has involved the refurbishment works to all five floors of the Civic Centre offices, from the top floor to reception. The works included phasing of each wing to suit the building occupants to cause minimal disruption to day to day workings of the council staff. These works include the complete strip out of floors, including partitions, flooring electrical strip out and asbestos vinyl tiles removal. The reinstatement works included the installation of new partitions to suit the unique layouts for each floor, flooring, decorating, suspended ceilings, new lighting and power and window repairs.
We commenced work in October 2018 and the works completed September 2020. Recent works include the refurbishment of lift lobbies and stairwell areas.